To avoid further potential problems, the following procedure should be
followed as closely as possible to get started.
- Start OBS, select the program source and the program frequency,
then type LOAD and immediately after MICRO. This is normally done by the
recommended PR:Name.OBS setup procedure, for project `` Name''.
- Tune the receivers.
- In parallel, you may initialize the antennas and subreflectors if not
done, open the central hub, etc... When antennas have been initialized,
select a strong continuum source to check pointing, type LOAD.
- As soon as receiver are tuned, use a CALIBRATE procedure (in INTER
mode). All receiver temperatures should be reasonable.
- Make an BANDPASS procedure to calibrate the IF passband
characteristic. Look at the result using CLIC. This checks the spectral
correlator up to a certain point. If anything is unusual, notify the
maintenance staff.
- Select a strong line source (for that frequency, see catalog of
strong line sources), and use an ONOFF procedure. Line should be detected
in all antennas.
- Select a strong continuum point source to determine delays on all
antennas if unknown.
- Make a POINT on that source. All antennas should be pointed.
- Eventually send the phase calibrator used for your program source,
and start interferometry. Phases on AFF should be constant.